Feeder/Substation Load Relief and Peak Load Management During High Load Season

MBESS Size 20 Ft Trailer / PROMIS (500 kW / 1 MWh), 16 Ft Trailer / Mini-PROMIS (250 kW / 500 kWh)​

Innoversa has deployed MBESS for 3 consecutive years to support the customer’s seasonal peak load challenges, delivering reliable, clean, and flexible power without the need for diesel generation.

Key Use Cases:​

  • Utilizing mobile energy storage as a complete replacement for diesel generators to provide temporary feeder and load relief.​
  • Supporting a vacation community during peak tourist seasons (8–10 weeks)​
  • Mitigating voltage drop issues caused by long single-phase feeder distances.​
  • Connection through a pole-mounted step-up transformer to efficiently supply peak demand.​
  • Charging during off-peak hours (1 AM – 6 AM) using pre-scheduled setpoints.​
  • Discharging during peak hours (10 AM – 10 PM) based on scheduled profiles and real-time voltage needs.​
  • Reactive power (Q) injection to maintain feeder voltage within acceptable limits.​
  • Volt-VAR control for dynamic voltage support and grid stability​
  • Active power (P) setpoint adjustment in response to voltage fluctuations​
  • Low Voltage Ride-Through (LVRT) enabled to ensure continuous operation during disturbances.

Customer Gain:​

  • Eliminated diesel usage, reducing fuel costs, emissions, and noise.​
  • Maintained stable voltage and improved power quality across the feeder.​
  • Enabled reliable service during peak demand without costly grid upgrades.​
  • Improved customer satisfaction in high-demand seasonal periods.​
  • Flexible, repeatable deployment year-over-year with minimal setup time.​
  • Enhanced grid resilience with advanced control capabilities and real-time response
Year Utilization Diesel Use (l/G) MBESS Use Fuel Saving
2022Diesel Only9,600 litres (2,536 gal)--
2023MBESS as Primary, Diesel as backup-16,586 kWh5,530 litres
20242 x MBESS, No Diesel-49,503 kWh16,501 litres
20252 x MBESS, No DieselPending DataPending DataPending Data